Summerland disaster
Contents |
[edit] Introduction
Opened in May 1971 and billed as the most innovative indoor entertainment centre in the world, the Summerland leisure complex on the Isle of Man was to suffer a catastrophic fire in August 1973 which killed 50 people, injured 80 and led to the destruction of the building. It was one of the first building fires in the UK to sound the alarm over the rapid flame-spread of some modern composite panels.
The £2m venue covered an area of 4,600m2 and had a total capacity of 10,000 people. It had five floors of holiday amusements and games, a roller-skating rink, children’s theatre, underground disco, dance floor, saunas, restaurants and public bars. Modern in every respect, the building was constructed using new techniques and materials and featured a state-of-the-art climate control system.
But it was designed by two different architects who did not coordinate. The result was a building which carried significant yet hidden shortcomings in its resistance to the spread of fire.
[edit] How it started
It began on the evening of August 2 1973. With around 3,000 people in the centre, three schoolboys from Liverpool – aged 12, 12 and 14 and smoking in an outside kiosk, discarded a match which started a small fire (it was said at the public enquiry that they may have also been playing with matches).
Once ablaze, the lightweight plastic structure collapsed against the exterior façade of the building which was clad in a profiled steel sheet covered on both sides by bitumen-coated asbestos (Galbestos). The fire spread to a part of the building (mainly the roof) clad in a highly flammable, transparent acrylic sheet material called Oroglas (subsequently called ‘horrorglass’). The material had been used by Buckminster Fuller in his Montreal pavilion (which burned in 1976).
Once the fire took hold, it spread quickly across the sheeting, up walls and across the roof. Contributing to the rapid fire spread were the air vents which were subsequently found not to have been adequately fire-stopped. Further fanning the fire was the acrylic sheet which once it started to melt, produced droplets of molten material which caused other fires. Furthermore, the open-plan design of much of the building may have resulted in spaces which acted as funnels to fuel the fire.
Although the acrylic sheeting contributed to the fire, it was regarded at the public enquiry as only a secondary cause: the majority of deaths had occurred due to the massive internal fire, before the Oroglas was set ablaze by fire emanating from within the building. It was concluded that it played no role in the spread and development of the fire inside the building. Indeed, the Galbestos and another material Decalin were seen as greater contributory causes.
[edit] Contributory factors to the disaster
- The misuse of new building materials.
- Two architects involved in the centre’s design did not coordinate with each other.
- Inadequate or lack of fire-stopping at service voids.
- Fire service only called 20 minutes after the fire started.
- Alarms did not go off as the wiring system had perished in the heat.
- Delayed evacuation – no organised attempt to evacuate the building – the alarm was raised by a ship two miles at sea.
- Inefficiencies on the part of the building’s management.
- Some fire doors may have been locked and people crushed as a result.
- Defects in the means of escape – staircases, exits and signage.
[edit] Consequences of the fire
It seems that the disaster at Summerland is a classic case of numerous factors which together produced a tragedy. As a result of the fire, changes to the building regulations were introduced to improve fire safety in buildings. The Fire Brigades’ Union demanded a new regime of comprehensive certification of building materials for the construction of entertainment and shopping complexes. The Union also called for fire regulations to be updated frequently.
No one was blamed for the blaze or the deaths and the coroner’s verdict was one of ‘misadventure’. The three boys from Liverpool – aged 12, 12 and 14 were ordered to pay small fines.
[edit] Related articles on Designing Buildings Wiki
- ACM cladding.
- Combustibility.
- Fire.
- Fire safety design.
- Glasgow School of Art fire.
- Grenfell Tower articles.
- Grenfell Tower fire.
- Grenfell Tower independent expert advisory panel.
- Grenfell Tower Inquiry.
- Hackitt report.
- HPL cladding.
- Rainscreen cladding.
- Ronan Point.
- Torre Windsor office building fire.
Featured articles and news
One of the most impressive Victorian architects. Book review.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.